Leave us a Message

Bombay High Court Upholds Arbitral Award While Rejecting Insurer’s Attempt to Split Insurance Claim

Overview

In this case, the Bombay High Court dealt with a challenge made under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute was pertaining to the interpretation of an arbitration clause in an Industrial Risk Insurance Policy(IARP) issued by United India Insurance Company Limited(UIICL) to UPL Limited.

The insurer accepted its liability as to repair expenses caused due to damage upon a gas turbine engine, but denied its liability towards the cost of overhauling. The Court had to examine whether the dispute was related to “liability” or “quantum” payable.


 

Facts of the Case

UPL Ltd., the respondent herein, took an IARP from UIICL, the petitioner, for its power plant in Gujarat, which operated through a gas turbine engine manufactured by General Electric(GE).

On 16 September 2001, it was observed that the engine had developed a fault. Further inspection revealed that there has been damage to the bearing assembly. The engine was sent to GE’s facility in Houston for repair. An overhaul of the engine was recommended and around the same time, the petitioner communicated that such overhaul was necessary to avoid any future risks.

Relying on the same, the respondent proceeded with the overhaul and a claim of nearly ?15 crores was raised. However, after receiving the details as to finances, the petitioner changed its own stance and stated that only the repairs which were connected to the accident would be covered and not the expenses as to complete overhauling, since these expenses were outside the policy coverage.

Following the same, petitioner released around ?7.69 crores as settlement. The respondent accepted the payment, but invoked arbitration for the remaining amount. The sole arbitrator ruled in favour of UPL, due to which, UIICL approached the High Court. 

 

Legal Issues

  1. Whether the dispute as to overhauling expenses constituted a dispute relating to “liability” or merely “quantum” under the policy.
  2. Whether partial payment made by the insurer amounted to admitting the liability sufficient to invoke arbitration.
  3. Whether an insurance claim arising from one accident can be split into separate components.
  4. Whether the arbitral award suffered from patent illegality requiring interference under Section 34.
  5. Whether the incident in question was the real cause behind the engine overhaul.

 

Decision

The petition was dismissed by the Bombay High Court and the award was upheld in the favour of UPL Ltd.

It was observed that once the insurer accepted the liability and partial payment was made, the dispute was regarding the extent of the payment payable under the policy. The dispute clearly came within the scope of “quantum” disputes under the arbitration clause.

The Court, while rejecting the arguments of the insurer, held that a claim arising from one incident cannot be divided into two parts only to avoid arbitration. It was also noted that the insurer’s earlier communication asked the insured to proceed with a complete overhaul, which made its later denial contradictory. 

The Court found no perversity in the decision of the sole arbitrator which stated that the accident triggered the internal damage leading to overhauling. The material placed on record, including the GE reports, backed up this conclusion. It was even observed that the engine had not reached the overhaul threshold of 50,000 operational hours. 

The Court held that no ground under Section 34 was satisfied and it refused to interfere with the award while directing the release of the deposited amount along with interest to the respondent insured.

 

Case Reference:- United India Insurance Company Limited Vs. UPL Limited Commercial Arbitration Petition (L) No. 10809 of 2024 With Interim Application (L) No. 11225 of 2024 With Interim Application (L) No. 11117 of 2024