Leave us a Message

Delhi High Court Reiterates the Scope of an “Award” Which Can be Challenged Under Section 34

Overview

The Delhi High Court in this matter dealt with a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996. An order passed by a sole arbitrator was challenged by the petitioner during the pendency of the proceedings on 13 January 2025. 

The tribunal via the impugned order dismissed two applications of the petitioner. One was for seeking permission to place additional documents on record, and the second was seeking an amendment to the statement of defence and counter-claim. 

The High Court had to decide upon the issue as to whether such an order could be treated as an interim award under the Act and therefore be challenged under Section 34.

 

Facts of the Case

The dispute arose between the parties from the contracts dated 15 July 2020 and 22 April 2021. Following the same, arbitration proceedings were commenced to resolve it. During the arbitration, after the pleadings were completed, a Statement of Defence and Counter-Claim was filed by Cinda Engineering, the petitioner herein. The matter then proceeded towards the evidence stage and on 10 September 2024, cross-examination of the witness of the petitioner was completed. 

Thereafter, the petitioner filed an application seeking permission to place additional documents on record on 11 October 2024 since those became relevant after the cross-examination of the respondent, CY Engineering.

This request was opposed by the respondent by alleging that the documents were always within the possession and knowledge of the petitioner and that no reasonable or satisfactory explanation was given by the petitioner as to the delay in producing the same. 

The petitioner, during the pendency of this application, on 13 December 2024, filed another application seeking permission to amend its Statement of Defence and Counter-Claim. It was claimed that the amendment was important to provide additional details regarding the “back charges” and related claims. 

Both the applications were dismissed by the tribunal. It was observed that the petitioner had sufficient opportunity to place the documents on record at initial stages of the proceeding. Aggrieved by the same, the petitioner approached the Delhi High Court under Section 34 of the Arbitration and Conciliation Act 1996. 

 

Legal Issues

  1. Whether rejection of an application for amendment and producing documents considered to be an “interim award” under the Arbitration Act.
  2. Whether the orders which are passed during the arbitration proceedings can be challenged under Section 34 of the Act.
  3. Whether addressing any challenges as to procedural orders, defeat the principle of minimum judicial interference in arbitration. 

 

Decision

The petition was dismissed by Delhi High Court. It was held that the order was a procedural order, and it did not qualify as an arbitral or interim award under the Act.

The Court observed that an interim award must determine a substantive issue between the parties. In the current scenario, the tribunal only rejected the belated requests by the petitioner for placing the additional documents on record and amendment to the pleadings. 

The original counterclaims of the petitioner were still pending before the tribunal and had not been rejected. It was also noted that the tribunal specifically clarified that it was not expressing any opinion as to the merits of the dispute. 

The Court emphasised that allowing a Section 34 challenge against everyday procedural orders would lead to unnecessary judicial interference, which eventually defeats the purpose of arbitration as an efficient mechanism. 

Finally, the Court concluded that the petition was not maintainable and dismissed it without costs.

 

Case Reference:- Cinda Engineering and Construction Private Limited Vs. CY Engineering India Private Limited   O.M.P. (COMM) 67/2025  (SJB, Before Harish Vaidyanathan, J.)