This case came before the Bombay High Court in an appeal against an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The appellant argued that the arbitrator had erred in granting compensation to the contractor, even though the contract had clauses that restricted such claims.
The High Court had to decide whether the award suffered from serious legal errors, or whether it was simply a case where the arbitrator had taken a view based on the material before him. The Court also had to keep in mind that under Sections 34 and 37 of the Arbitration Act, courts cannot interfere with an award just because another view is possible.
The dispute arose from a contract between the parties for repair and restoration of 19 minor irrigation tanks in Beed District, Maharashtra. The offer of Respondent for the tender floated was accepted by the Appellant and a work order dated 17 November 2006 was issued. The deadline for the completion of the work allotted was 16 November 2007.
According to the claimant contractor, the department breached the conditions required to be fulfilled under the contract before the work could properly begin, due to which the project took longer than expected and the contractor claimed financial loss.
After trying to resolve the issue through the dispute resolution mechanism provided under the contract, and later through a special civil suit, the matter was transferred to the Commercial Court which further, with the consent of both the parties, referred it to arbitration in 2017.
On 2 February 2019, the arbitral award was delivered under which some claims were rejected, but compensation was granted wherever deemed reasonable including overhead losses, reduced productivity, delayed payments, price escalation, and refund of royalty deductions. In total, around Rs. 10.54 crores was awarded with 12% interest.
The government challenged the award under Section 34, but the Commercial Court dismissed the challenge on 12 April 2022. The present appeal was then filed under Section 37 of the Arbitration and Conciliation Act, 1996.
Legal Issues
Decision
The High Court dismissed the appeal. The Court noted that the government had participated in the arbitration proceedings without raising any objections as to the jurisdiction at the proper stage. As per the court, such objections cannot not be raised later.
On the main issue, the Court observed that the arbitrator had committed no error in examining both the contract and the evidence. The arbitrator was correct to find out that the delay was due to the department’s own actions. Once such a finding was recorded, the department could not rely on restrictive clauses to deny compensation.
The Court made it clear that interpretation of a contract is for the arbitrator to address and decide. Under Sections 34 and 37 of the Act, courts cannot reassess evidence or substitute their own view unless the award is illegal or unreasonable on the face of it. In this case, no such serious defect was found.
Accordingly, the arbitral award was upheld, and the appeal was dismissed.
Case Reference :- Commercial Arbitration Appeal No. 2 of 2022 and Civil Application No. 10992 of 2022 (2JB, Arun R. Pedneker and Vaishali Patil Jadhav JJ., delivered by Arun R. Pedneker, J.)
Disclaimer
In Compliance with Indian Regulations, Kindly Review the User Acknowledgement and Disclaimer below and then Proceed.
User Acknowledgement
By proceeding further and clicking on the "ACCEPT" button herein below, I acknowledge that I of my own accord wish to know more about Law Senate (LS) for my own information and use. I further acknowledge that there has been no solicitation, invitation or inducement of any sort whatsoever from Law Senate (LS) or any of its members to create an Attorney-Client relationship through this website. I further acknowledge having read and understood the Disclaimer below
This website (www.lawsenate.com) is a resource for informational purposes only and is intended, but not promised or guaranteed, to be correct, complete, and up-to-date. Law Senate (LS) does not warrant that the information contained on this website is accurate or complete, and hereby disclaims any and all liability to any person for any loss or damage caused by errors or omissions, whether such errors or omissions result from negligence, accident or any other cause. Law Senate (LS) further assumes no liability for the interpretation and/or use of the information contained on this website, nor does it offer a warranty of any kind, either expressed or implied. The owner/Partners of this website do not intend links from this site to other internet websites to be referrals to, endorsements of, or affiliations with the linked entities. Law Senate (LS) is not responsible for, and makes no representations or warranties about, the contents of Web sites to which links may be provided from this Web site.
This website is not intended to be a source of advertising or solicitation and the contents of the website should not be construed as legal advice. The reader should not consider this information to be an invitation for a lawyer-client relationship and should not rely on information provided herein and should always seek the advice of competent counsel licensed to practice in the reader's country/state. Transmission, receipt or use of this website does not constitute or create a lawyer-client relationship. No recipients of content from this website should act, or refrain from acting, based upon any or all of the contents of this site.
Furthermore, the owner of this website does not wish to represent anyone desiring representation based solely upon viewing this Web site or in a country/state where this website fails to comply with all laws and ethical rules of that state. Finally, the reader is warned that the use of Internet e-mail for confidential or sensitive information is susceptible to risks of lack of confidentiality associated with sending email over the Internet.
As per the rules of the Bar Council of India, lawyers are not permitted to advertise themselves. The information about the Firm, its Key Practice Areas or its Key Team Members provided under this website is only for informational purposes and it should not be interpreted as soliciting or advertisement of any nature whatsoever.
The information provided on this website is for general information only. It is not intended to create or promote an attorney-client relationship and does not constitute and should not be relied upon or construed as legal advice.
Communications via this website also do not create an attorney-client relationship. Visitor should always seek appropriate professional advice before acting on the basis of any information contained herein.